Basic oxygen furnace

Also called BOF

A pear-shaped vessel where oxygen blown into molten iron burns out its carbon to make steel.

The furnace is charged with about 70% molten iron from the blast furnace and 30% scrap. High-purity oxygen is blown in through a water-cooled lance. It burns away carbon and impurities, and the reactions give off enough heat to melt the scrap with no other fuel. A furnace holds up to 400 tons, and a heat takes 25 to 45 minutes.